123456789101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960616263646566676869707172737475767778798081828384858687888990919293949596979899100101102103104105106107108109110111112113114115116117118119120121122123124125126127128129130131132133134135136137138139140141142143144145146147148149150151152153154155156157158159160161162163164165166167168169170171172173174175176177178179180181182183184185186187188189190191192193194195196197198199200
  1. <?php
  2. $lang->milestone->common = $lang->projectCommon . '里程碑报告';
  3. $lang->milestone->index = '报告首页';
  4. $lang->milestone->title = '里程碑报告';
  5. $lang->milestone->name = '里程碑名称';
  6. $lang->milestone->stage = '里程碑阶段';
  7. $lang->milestone->save = '保存';
  8. $lang->milestone->indexAction = '里程碑报告';
  9. $lang->milestone->startedWeeks = '开始周数';
  10. $lang->milestone->finishedWeeks = '结束周数';
  11. $lang->milestone->offset = '里程碑工期偏差';
  12. $lang->milestone->processCommon = $lang->projectCommon . '当前进展状况';
  13. $lang->milestone->process = $lang->projectCommon . '进度';
  14. $lang->milestone->executionCost = $lang->projectCommon . '成本';
  15. $lang->milestone->toNow = '到目前为止';
  16. $lang->milestone->targetRange = '目标控制范围';
  17. $lang->milestone->ge = '大于等于';
  18. $lang->milestone->le = '小于等于';
  19. $lang->milestone->analysis = '分析结果';
  20. $lang->milestone->PV = '计划完成的工作(PV)';
  21. $lang->milestone->EV = '实际完成的工作(EV)';
  22. $lang->milestone->AC = '实际花费的成本(AC)';
  23. $lang->milestone->SPI = $lang->projectCommon . '进度绩效(SPI)';
  24. $lang->milestone->CPI = $lang->projectCommon . '成本绩效(CPI)';
  25. $lang->milestone->SV = '进度偏差率(SV%)';
  26. $lang->milestone->CV = '成本偏差率(CV%)';
  27. $lang->milestone->workHours = '工作量(人时)';
  28. $lang->milestone->allStage = '工程阶段';
  29. $lang->milestone->devHours = '研发工作量';
  30. $lang->milestone->toHours = '返工工作量';
  31. $lang->milestone->reviewHours = '评审工作量';
  32. $lang->milestone->qaHours = '测试工作量';
  33. $lang->milestone->rowSummary = '工作量小计';
  34. $lang->milestone->rowPercent = '分布百分比(%)';
  35. $lang->milestone->colPercent = '占工作量百分比(%)';
  36. $lang->milestone->colSummary = '总和';
  37. $lang->milestone->qatoDev = '测试研发比';
  38. $lang->milestone->executionRisk = '5.' . $lang->projectCommon . '风险(优先最高的前五项风险)';
  39. $lang->milestone->riskCountermove = '风险对策';
  40. $lang->milestone->riskDescriptio = '风险描述';
  41. $lang->milestone->riskPossibility = '可能性';
  42. $lang->milestone->riskSeriousness = '严重性';
  43. $lang->milestone->riskFactor = '风险系数';
  44. $lang->milestone->riskMeasures = '风险对策';
  45. $lang->milestone->riskAccumulate = '累积的高风险';
  46. $lang->milestone->otherIssue = '其它问题';
  47. $lang->milestone->issueSolutions = '问题及解决建议';
  48. $lang->milestone->issueDescription = '问题描述';
  49. $lang->milestone->issuePropose = '解决建议';
  50. $lang->milestone->demandStatus = "4.{$lang->SRCommon}状况分析";
  51. $lang->milestone->storyUnit = '单位:Item';
  52. $lang->milestone->engineeringStage = '工程阶段';
  53. $lang->milestone->rateChange = '需求变化率';
  54. $lang->milestone->originalStory = '原始需求数量';
  55. $lang->milestone->modifyNumber = '变更后需求总数';
  56. $lang->milestone->changeStory = '变更的需求数';
  57. $lang->milestone->paogressForecast = $lang->projectCommon . '进展预测';
  58. $lang->milestone->duration = '工期(天)';
  59. $lang->milestone->cost = '成本(人时)';
  60. $lang->milestone->forecastResults = '预测结果分析';
  61. $lang->milestone->plannedValue = '计划值';
  62. $lang->milestone->predictedValue = '预测值';
  63. $lang->milestone->predictedValueDesc = '计算公式:如果' . $lang->projectCommon . '进度绩效(SPI)=0,那么预测值=0,否则,预测值=计划值 除以 ' . $lang->projectCommon . '进度绩效(SPI)';
  64. $lang->milestone->periodDeviation = '工期偏差';
  65. $lang->milestone->costDeviation = '成本偏差';
  66. $lang->milestone->nextStage = '下一里程碑阶段';
  67. $lang->milestone->overallProject = $lang->projectCommon . '总体';
  68. $lang->milestone->corrective = '纠偏措施';
  69. $lang->milestone->timeOverrun = '总工期将超出:%s天。';
  70. $lang->milestone->costOverrun = '总成本将超出:%s个单位。';
  71. $lang->milestone->saveOtherProblem = '保存其他问题';
  72. $lang->milestone->chart = new stdclass();
  73. $lang->milestone->chart->title = '到目前为止' . $lang->projectCommon . '进展趋势图';
  74. $lang->milestone->chart->time = '第';
  75. $lang->milestone->chart->week = '周';
  76. $lang->milestone->chart->month = '月';
  77. $lang->milestone->chart->workhour = '研发工作量分析图';
  78. $lang->milestone->otherproblem = '6.其它问题';
  79. $lang->milestone->problemandsuggest = '问题及解决建议';
  80. $lang->milestone->suggest = '解决建议';
  81. $lang->milestone->needhelp = '是否需要高层支持?';
  82. $lang->milestone->prodescr = '问题描述';
  83. $lang->milestone->reviewHoursTip = '评审工作量 = 评审时长 * 评审人数';
  84. $lang->milestone->toHoursTip = '返工工作量统计的是研发任务被激活之后,重新消耗的工时';
  85. $lang->milestone->startedWeekTip = '统计项目开始时间到当前里程碑开始时间的周数';
  86. $lang->milestone->finishedWeekTip = '统计项目开始时间到当前里程碑结束时间的周数';
  87. $lang->milestone->quality = new stdclass();
  88. $lang->milestone->quality->total = '合计';
  89. $lang->milestone->quality->identify = '缺陷识别阶段';
  90. $lang->milestone->quality->injection = '缺陷注入阶段';
  91. $lang->milestone->quality->scale = '规模';
  92. $lang->milestone->quality->identifyRate = '缺陷识别率';
  93. $lang->milestone->quality->injectionRate = '缺陷注入率';
  94. $lang->milestone->options = '操作';
  95. $lang->milestone->milestoneHelpNotice = <<<EOD
  96. <h2>PV 计划完成的工作</h2>
  97. 计算方式:
  98. <br />1)任务所属阶段是当前里程碑,累加预计工时
  99. <br />2)当前里程碑阶段之前的所有阶段下的任务,累加预计工时
  100. <p>统计范围:</p>
  101. 1)为避免重复计算,只包含子任务,不包括父任务
  102. <br />2)不包括已删除的任务
  103. <br />3)不包括已取消的任务
  104. <br />4)不包括已删除执行中的任务
  105. <h2>EV实际完成的工作</h2>
  106. 计算方式:
  107. <br />1)任务所属阶段是当前里程碑:
  108. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已完成,累加预计工时
  109. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已关闭且关闭原因为已完成,累加预计工时
  110. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为进行中、已暂停,累加 预计工时×完成进度
  111. <br />2)当前里程碑阶段之前的所有阶段下的任务:
  112. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已完成,累加预计工时
  113. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为已关闭且关闭原因为已完成,累加预计工时
  114. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;任务状态为进行中、已暂停,累加 预计工时×完成进度
  115. <p>统计范围:</p>
  116. 1)为避免重复计算,只包含子任务,不包括父任务
  117. <br />2)不包括已删除的任务
  118. <br />3)不包括已取消的任务
  119. <br />4)不包括已删除执行中的任务
  120. <br />5)消耗工时不为0的任务
  121. <br />6)完成进度=已消耗工时÷(已消耗工时+剩余工时)
  122. <h2>AC 实际花费(消耗)的成本</h2>
  123. 计算方式:
  124. <br />1)当前里程碑中所有消耗的工时
  125. <br />2)当前里程碑阶段之前的所有阶段下消耗的工时
  126. <p>统计范围:</p>
  127. 1)消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
  128. <br />2)为避免重复计算,只包含子任务,不包括父任务
  129. <br />3)包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
  130. <br />4)包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
  131. <br />5)包括取消的任务、问题、风险的耗时
  132. <h2>SV(%)进度偏差率</h2>
  133. 计算方式:SV(%) = -1 * (1 - (EV / PV))%
  134. <h2>CV(%) 成本偏差率</h2>
  135. 计算方式:CV(%) = -1 * (1 - (EV / AC))%
  136. <h2>SPI 进度性能指标</h2>
  137. 计算方式:SPI = EV / PV
  138. <h2>CPI成本性能指标</h2>
  139. 计算方式:CPI = EV / AC
  140. EOD;
  141. $lang->milestone->soFarHelpNotice = <<<EOD
  142. <h2>PV计划完成的工作</h2>
  143. 计算方式:
  144. <br />1)任务预计截止日期在今天结束时间之前,累加预计工时
  145. <br />2)任务预计开始日期小于今天结束时间,截止日期大于今天结束时间,累加(任务的预计工时 ÷ 任务工期天数)× 任务预计开始到本周结束日期的天数
  146. <p>统计范围:</p>
  147. 1)为避免重复计算,只包含子任务,不包括父任务
  148. <br />2)不包括删除的任务
  149. <br />3)不包括取消的任务
  150. <br />4)不包括已删除执行中的任务
  151. <br />5)今天结束时间是今天的23:59:59
  152. <br />6)任务未填写预计开始日期,预计开始日期默认取任务所属阶段的计划开始日期
  153. <br />7)任务未填写预计截止日期,预计截止日期默认取任务所属阶段的计划完成日期
  154. <br />8)计算公式只计算工作日
  155. <h2>EV实际完成的工作</h2>
  156. 计算方式:
  157. <br />1)任务状态为已完成,累加预计工时
  158. <br />2)任务状态为已关闭且关闭原因为已完成,累加预计工时
  159. <br />3)任务状态为进行中、已暂停,累加 预计工时×完成进度
  160. <p>统计范围:</p>
  161. 1)今天结束时间之前,今天结束时间是今天的23:59:59
  162. <br />2)为避免重复计算,只包含子任务,不包括父任务
  163. <br />3)不包括已删除的任务
  164. <br />4)不包括已取消的任务
  165. <br />5)不包括已删除执行中的任务
  166. <br />6)消耗工时不为0的任务
  167. <br />7)完成进度=已消耗工时÷(已消耗工时+剩余工时)
  168. <h2>AC 实际花费(消耗)的成本</h2>
  169. 计算方式:
  170. <br />1)累加今天结束时间之前所有消耗的工时
  171. <p>统计范围:</p>
  172. 1)消耗的工时包括任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
  173. <br />2)为避免重复计算,只包含子任务,不包括父任务
  174. <br />3)包括已删除的任务、需求、Bug、用例、版本、测试单、问题、风险、文档、评审的耗时
  175. <br />4)包括已删除执行中任务、需求、Bug、用例、版本、测试单、文档的耗时
  176. <br />5)包括取消的任务、问题、风险的耗时
  177. <br />6)今天结束时间是今天的23:59:59
  178. <h2>SV(%)进度偏差率</h2>
  179. 计算方式:SV(%) = -1 * (1 - (EV / PV))%
  180. <h2>CV(%) 成本偏差率</h2>
  181. 计算方式:CV(%) = -1 * (1 - (EV / AC))%
  182. <h2>SPI 进度性能指标</h2>
  183. 计算方式:SPI = EV / PV
  184. <h2>CPI成本性能指标</h2>
  185. 计算方式:CPI = EV / AC
  186. EOD;