en.php 12 KB

123456789101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960616263646566676869707172737475767778798081828384858687888990919293949596979899100101102103104105106107108109110111112113114115116117118119120121122123124125126127128129130131132133134135136137138139140141142143144145146147148149150151152153154155156157158159160161162163164165166167168169170171172173174175176177178179180181182183184185186187188189190191192193194195196197198199200
  1. <?php
  2. $lang->milestone->common = $lang->projectCommon . 'Milestone Report';
  3. $lang->milestone->index = 'Milestone Home';
  4. $lang->milestone->title = 'Milestone Report';
  5. $lang->milestone->name = 'Milestone Name';
  6. $lang->milestone->stage = 'Milestone Stage';
  7. $lang->milestone->save = 'Save';
  8. $lang->milestone->indexAction = 'Milestone Report';
  9. $lang->milestone->startedWeeks = 'Started Weeks';
  10. $lang->milestone->finishedWeeks = 'Finished Weeks';
  11. $lang->milestone->offset = 'Milestone Deviation';
  12. $lang->milestone->processCommon = $lang->projectCommon . 'Current Status';
  13. $lang->milestone->process = $lang->projectCommon . 'Schedule';
  14. $lang->milestone->executionCost = $lang->projectCommon . 'Cost';
  15. $lang->milestone->toNow = 'So far';
  16. $lang->milestone->targetRange = 'Target Range';
  17. $lang->milestone->ge = 'ge';
  18. $lang->milestone->le = 'le';
  19. $lang->milestone->analysis = 'Analysis';
  20. $lang->milestone->PV = 'The work to be done(PV)';
  21. $lang->milestone->EV = 'Actual work done(EV)';
  22. $lang->milestone->AC = 'Actual cost(AC)';
  23. $lang->milestone->SPI = $lang->projectCommon . 'schedule performance(SPI)';
  24. $lang->milestone->CPI = $lang->projectCommon . 'cost performance(CPI)';
  25. $lang->milestone->SV = 'Rate of progress deviation(SV%)';
  26. $lang->milestone->CV = 'Cost deviation rate(CV%)';
  27. $lang->milestone->workHours = 'Workload (man-hour)';
  28. $lang->milestone->allStage = 'Project Stage';
  29. $lang->milestone->devHours = 'Development Workload';
  30. $lang->milestone->toHours = 'Rework Workload';
  31. $lang->milestone->reviewHours = 'Review Hours';
  32. $lang->milestone->qaHours = 'Test Workload';
  33. $lang->milestone->rowSummary = 'Workload Subtotal';
  34. $lang->milestone->rowPercent = 'Percentage Distribution(%)';
  35. $lang->milestone->colPercent = 'Percentage of workload(%)';
  36. $lang->milestone->colSummary = 'Total';
  37. $lang->milestone->qatoDev = 'Test Development ratio';
  38. $lang->milestone->executionRisk = '5.' . $lang->projectCommon . 'Risks (top five highest priority risks)';
  39. $lang->milestone->riskCountermove = 'Risk Countermove';
  40. $lang->milestone->riskDescriptio = 'Risk Description';
  41. $lang->milestone->riskPossibility = 'Risk Possibility';
  42. $lang->milestone->riskSeriousness = 'Risk Seriousness';
  43. $lang->milestone->riskFactor = 'Risk Factor';
  44. $lang->milestone->riskMeasures = 'Risk Measures';
  45. $lang->milestone->riskAccumulate = 'Risk Accumulate';
  46. $lang->milestone->otherIssue = 'Other Issue';
  47. $lang->milestone->issueSolutions = 'Issue Solutions';
  48. $lang->milestone->issueDescription = 'Issue Description';
  49. $lang->milestone->issuePropose = 'Issue Propose';
  50. $lang->milestone->demandStatus = '4.Customer Demand Analysis';
  51. $lang->milestone->storyUnit = 'Unit:Item';
  52. $lang->milestone->engineeringStage = 'Engineering Stage';
  53. $lang->milestone->rateChange = 'Rate of change in demand';
  54. $lang->milestone->originalStory = 'Quantity of original demand';
  55. $lang->milestone->modifyNumber = 'Total post-change requirements';
  56. $lang->milestone->changeStory = 'Number of changed requirements';
  57. $lang->milestone->paogressForecast = $lang->projectCommon . 'Forecast';
  58. $lang->milestone->duration = 'Construction period(day)';
  59. $lang->milestone->cost = 'Cost(hours)';
  60. $lang->milestone->forecastResults = 'Forecast Results';
  61. $lang->milestone->plannedValue = 'Planned Value';
  62. $lang->milestone->predictedValue = 'Predicted Value';
  63. $lang->milestone->predictedValueDesc = 'Rentenformel (Germany):If the execution' . $lang->projectCommon .'performance(SPI)=0,So the predicted value=0,Otherwise,Predicted value=Planned value divided by Project schedule performance(SPI)';
  64. $lang->milestone->periodDeviation = 'Period Deviation';
  65. $lang->milestone->costDeviation = 'Cost Deviation';
  66. $lang->milestone->nextStage = 'Next Stage';
  67. $lang->milestone->overallProject = 'Overall' . $lang->projectCommon;
  68. $lang->milestone->corrective = 'Corrective Measure';
  69. $lang->milestone->timeOverrun = 'The total construction time will exceed:%s day.';
  70. $lang->milestone->costOverrun = 'The total cost will exceed:%s unit';
  71. $lang->milestone->saveOtherProblem = 'Save Other Problem';
  72. $lang->milestone->chart = new stdclass();
  73. $lang->milestone->chart->title = 'Trend Chart of execution'. $lang->projectCommon . 'to date';
  74. $lang->milestone->chart->time = 'No';
  75. $lang->milestone->chart->week = 'week';
  76. $lang->milestone->chart->month = 'month';
  77. $lang->milestone->chart->workhour = 'Development Workload Analysis Chart';
  78. $lang->milestone->otherproblem = '6.Other Problem';
  79. $lang->milestone->problemandsuggest = 'Problem and Suggest';
  80. $lang->milestone->suggest = 'Suggest';
  81. $lang->milestone->needhelp = 'Does it require high-level support?';
  82. $lang->milestone->prodescr = 'Problem Description';
  83. $lang->milestone->reviewHoursTip = 'Review Hours = Reviewed Hours * Reviewer Count';
  84. $lang->milestone->toHoursTip = "Rework Workload counts the Reconsumed work hours after task is activated";
  85. $lang->milestone->startedWeekTip = 'Counts the number of weeks between the project actual begin date and the current milestone actual begin date';
  86. $lang->milestone->finishedWeekTip = 'Counts the number of weeks between the project actual begin date and the current milestone actual end date';
  87. $lang->milestone->quality = new stdclass();
  88. $lang->milestone->quality->total = 'Total';
  89. $lang->milestone->quality->identify = 'Defect identification phase';
  90. $lang->milestone->quality->injection = 'Defect injection phase';
  91. $lang->milestone->quality->scale = 'Scale';
  92. $lang->milestone->quality->identifyRate = 'Defect recognition rate';
  93. $lang->milestone->quality->injectionRate = 'Defect injection rate';
  94. $lang->milestone->options = 'Options';
  95. $lang->milestone->milestoneHelpNotice = <<<EOD
  96. <h2>PV Planned Value</h2>
  97. Calculation method:
  98. <br />1) The phase of the task is the current milestone, and the estimated man hours are accumulated
  99. <br />2) The tasks under all stages before the current milestone stage, and the estimated man hours are accumulated
  100. <p>Statistical range:</p>
  101. 1) To avoid repeated calculation, only child tasks are included, not parent tasks
  102. <br />2) Exclude deleted tasks
  103. <br />3) Exclude canceled tasks
  104. <br />4) Exclude tasks in deleted execution
  105. <h2>EV Earned Value</h2>
  106. Calculation method:
  107. <br />1) The phase of the task is the current milestone:
  108. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is done, and the estimated work hours are accumulated
  109. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is closed and the reason for closing is done, and the estimated work hours are accumulated
  110. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is in doing, suspended, and the estimated work hours are accumulated × progress
  111. <br />2) Tasks under all phases before the current milestone phase:
  112. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is done, and the estimated work hours are accumulated
  113. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is closed and the reason for closing is done, and the estimated work hours are accumulated
  114. <br />&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;The task status is in doing, suspended, and the estimated work hours are accumulated × progress
  115. <p>Statistical range:</p>
  116. 1) To avoid repeated calculation, only child tasks are included, not parent tasks
  117. <br />2) Exclude deleted tasks
  118. <br />3) Exclude canceled tasks
  119. <br />4) Exclude tasks in deleted execution
  120. <br />5) Tasks with consumed work not 0
  121. <br />6) Progress= consumed man hours ÷(consumed man hours+remaining man hours)
  122. <h2>AC Actual Cost</h2>
  123. Calculation method:
  124. <br />1) All consumed man hours in the current milestone
  125. <br />2) Man hours consumed in all stages before the current milestone stage
  126. <p>Statistical range:</p>
  127. 1) All consumed man hours include task, requirement, bug, use case, version, test sheet, problem, risk, document and review time
  128. <br />2) To avoid repeated calculation, only child tasks are included, not parent tasks
  129. <br />3) Including deleted tasks, requirements, bugs, use cases, versions, test sheets, problems, risks, documents, and time consuming of reviews
  130. <br />4) Including the time consumption of deleted tasks, requirements, bugs, use cases, versions, test sheets and documents in execution
  131. <br />5) Including the time consumption of cancelled tasks, problems and risks
  132. <h2>SV(%) Schedule Variance</h2>
  133. Calculation method: SV(%) = -1 * (1 - (EV / PV))%
  134. <h2>CV(%) Cost Variance</h2>
  135. Calculation method: CV(%) = -1 * (1 - (EV / AC))%
  136. <h2>SPI Schedule Performance Index</h2>
  137. Calculation method: SPI = EV / PV
  138. <h2>CPI Cost Performance Index</h2>
  139. Calculation method: CPI = EV / AC
  140. EOD;
  141. $lang->milestone->soFarHelpNotice = <<<EOD
  142. <h2>PV Planned Value</h2>
  143. Calculation method:
  144. <br />1)The expected deadline of the task is before today's end time, and the expected work is accumulated
  145. <br />2)The estimated start date of a task is less than today's end time, and the end date is greater than today's end time. Accumulate (the estimated work hours of the task ÷ the task duration days) × The number of days from the expected start of the task to the end of this week
  146. <p>Statistical range:</p>
  147. 1) To avoid repeated calculation, only child tasks are included, not parent tasks
  148. <br />2) Exclude deleted tasks
  149. <br />3) Exclude canceled tasks
  150. <br />4) Exclude tasks in deleted execution
  151. <br />5)Today's end time is today's 23:59:59
  152. <br />6)No expected start date is filled in the task. The expected start date defaults to the planned start date of the phase to which the task belongs
  153. <br />7)No expected end date is filled in the task. By default, the expected end date is the planned completion date of the phase to which the task belongs
  154. <br />8)Calculation formula only calculates working days
  155. <h2>EV Earned Value</h2>
  156. Calculation method:
  157. <br />1) The task status is done, and the estimated work hours are accumulated
  158. <br />2) The task status is closed and the reason for closing is done, and the estimated work hours are accumulated
  159. <br />3) The task status is in doing, suspended, and the estimated work hours are accumulated × progress
  160. <p>Statistical range:</p>
  161. 1) Before today's end time, today's end time is 23:59:59
  162. <br />2) To avoid repeated calculation, only child tasks are included, not parent tasks
  163. <br />3) Exclude deleted tasks
  164. <br />4) Exclude canceled tasks
  165. <br />5) Exclude tasks in deleted execution
  166. <br />6) Tasks with consumed work not 0
  167. <br />7) Progress=consumed man hours ÷ (consumed man hours+remaining man hours)
  168. <h2>AC Actual Cost</h2>
  169. Calculation method:
  170. <br />1) Accumulate all consumed man hours before today's end time
  171. <p>Statistical range:</p>
  172. 1) All consumed man hours include task, requirement, bug, use case, version, test sheet, problem, risk, document and review time
  173. <br />2) To avoid repeated calculation, only child tasks are included, not parent tasks
  174. <br />3) Including deleted tasks, requirements, bugs, use cases, versions, test sheets, problems, risks, documents, and time consuming of reviews
  175. <br />4) Including the time consumption of deleted tasks, requirements, bugs, use cases, versions, test sheets and documents in execution
  176. <br />5) Including the time consumption of cancelled tasks, problems and risks
  177. <br />6)Today's end time is today's 23:59:59
  178. <h2>SV(%) Schedule Variance</h2>
  179. Calculation method: SV(%) = -1 * (1 - (EV / PV))%
  180. <h2>CV(%) Cost Variance</h2>
  181. Calculation method: CV(%) = -1 * (1 - (EV / AC))%
  182. <h2>SPI Schedule Performance Index</h2>
  183. Calculation method: SPI = EV / PV
  184. <h2>CPI Cost Performance Index</h2>